Temporary Shoring: Types, Cal/OSHA Rules & When You Need It
Temporary shoring is a support system that carries the load of a structure, or part of one, for as long as that structure cannot safely carry the load itself. On a building job, that usually means holding up a slab during a pour, a wall during an opening, or a frame during a repair or retrofit, then coming out once the permanent structure takes the load back.
This guide is written for general contractors planning that work in Los Angeles and Orange County. It covers the main types of temporary shoring, what Cal/OSHA requires before the shores go in, and how to plan the job. One note on scope: it covers vertical and structural shoring above grade, not trench or excavation shoring, which is a different discipline with its own rules.
What Is Temporary Shoring?
Temporary shoring is any engineered support put in place for a limited period to carry dead load, live load and construction load while the permanent structure is incomplete, weakened or being changed. It is designed for one job’s loads, installed, inspected, and then removed in a planned sequence.
It shows up in three situations on most building projects: new concrete construction, where shores hold the formwork and wet concrete; renovation and repair, where part of a structure is opened up or replaced; and seismic retrofit, where existing members are supported while new ones are added. For the bigger picture, see our guide to shoring in construction.
Types of Temporary Shoring
The right system depends on which way the load is moving and what has to stay open around it. These are the common types on LA building jobs.
| What it supports | Typical use | |
|---|---|---|
| Vertical post shores and shoring towers | Slabs, beams and decks from below | Elevated concrete pours, reshoring, floor repairs |
| Raker shores | Walls, from the side at an angle | Bulging or damaged walls, facade retention |
| Flying (horizontal) shores | Two facing walls, braced against each other | Gaps left when a building between two others is removed |
| Needle beams with dead shores | A wall, through a new opening | Cutting doorways or openings in bearing walls |
| Falsework | Formwork and wet concrete for elevated work | Bridge decks, transfer beams, large elevated slabs |
Each of these has its own detail. We break down how raker shores brace a wall and when a needle beam is the right call in separate guides, and falsework vs. formwork in another.
When Do You Need Temporary Shoring?
You need temporary shoring whenever a member will carry more load than it can safely take during construction, or will lose support it normally has. If an engineer, the drawings or the inspector expects the load path to be interrupted, plan shoring before the work starts, not after a problem shows up.
- Elevated concrete. Slabs and beams need shores until the concrete reaches the strength the engineer specifies, and often reshoring below that. We cover shoring vs reshoring in a separate guide.
- Openings in bearing walls. New doors, windows or storefronts cut into a wall that carries load from above.
- Column or beam replacement. Removing or repairing a damaged member means the load has to go somewhere else first.
- Seismic and soft-story retrofit. Existing framing is supported while new steel or concrete is added. See our notes on shoring for seismic retrofit.
- Fire, impact or deterioration damage. Stabilizing a structure so crews can work safely while repairs are designed.
Cal/OSHA Requirements for Temporary Shoring
In California, vertical shoring is governed by Title 8, Section 1717 of the Construction Safety Orders, and the permit trigger sits in Section 341. These are the rules that shape most shoring plans on our jobs. Always confirm the current text and any project-specific requirements with your engineer.
| Requirement | Source | |
|---|---|---|
| Who must sign the design? | A California-registered civil engineer when height from sill to soffit exceeds 14 ft, horizontal spans exceed 16 ft, or traffic passes through the shoring | Title 8 §1717(b)(1) |
| What about smaller installations? | The shoring layout is signed by a registered civil engineer, the manufacturer’s authorized representative, or a qualified licensed contractor’s representative | Title 8 §1717(b)(2) |
| What design load applies? | At least 100 lb per sq ft combined live and dead load, with at least 20 lb per sq ft for live load and formwork on top of the concrete weight | Title 8 §1717(a)(2) |
| Is an inspection required? | Yes, before concrete is placed, with written certification kept on site | Title 8 §1717(c) |
| When is a permit needed? | When scaffolding, vertical shoring or falsework is intended to be more than 36 ft high when completed | Title 8 §341 |
Two rules are easy to miss. First, Section 1717 says the falsework plan or shoring layout “shall be available on the job site at all times.” Second, all vertical supports must sit on “a properly compacted and reasonably level and stable base,” so soil and sill conditions belong in the plan, not just the shore capacity. Read the full text of Title 8 Section 1717 and the permit rules in Title 8 Section 341.
How to Plan a Temporary Shoring Job
A good shoring job is mostly decided before the first shore goes up. This is the order we work through with GCs.
- Define the load and the duration. What is being supported, how much it weighs, and for how long.
- Check height and span against Section 1717. That decides whether a registered civil engineer must design and sign the plan.
- Confirm the base. Slab-on-grade, compacted soil or an existing floor all change sill and plate design.
- Get a signed shoring plan. Our licensed engineers design and stamp Golden Scaffold’s shoring plans, so design and installation are coordinated from the start.
- Pull the permit if you are over 36 ft. Build the Cal/OSHA permit into the schedule.
- Inspect and certify before loading. Keep the written certification on site.
- Plan removal and reshoring. Shores come out only when the engineer’s strength requirement is met, in the order the plan calls for.
Temporary Shoring vs. a Temporary Shoring Wall
The two names sound alike but solve different problems. Temporary shoring, as used here, holds up a structure from below or from the side. A temporary shoring wall holds back soil or a structure laterally along a line. If that is your situation, read our guide to the temporary shoring wall.
Temporary Shoring for LA and Orange County Projects
Golden Scaffold provides heavy-duty structural shoring and temporary support systems for construction, renovation and structural concrete projects across Los Angeles and Orange County, with flexible rental durations. Our licensed engineers design and stamp Golden Scaffold’s shoring plans, and our team brings 35+ years of combined experience (CA License #1109519).
Get a shoring quote or call (424) 476-4426.
Frequently Asked Questions About Temporary Shoring
What is temporary shoring?
Temporary shoring is a support system installed for a limited period to carry the load of a structure, or part of one, while it cannot safely carry that load itself. On building jobs it is used during concrete pours, renovation, structural repair and retrofit, and it is removed once the permanent structure takes the load back.
What is the difference between temporary and permanent shoring?
Temporary shoring is removed when the work is done, such as shores under a slab until the concrete gains strength. Permanent shoring stays as part of the finished structure, such as a retaining system left in the ground. This guide covers temporary vertical and structural shoring above grade, not excavation support.
Does temporary shoring need an engineer in California?
Often, yes. Cal/OSHA Title 8 Section 1717 requires design calculations and working drawings signed by a California-registered civil engineer when falsework or vertical shoring is taller than 14 feet from sill to soffit, has spans over 16 feet, or allows vehicle or rail traffic through it.
Do I need a Cal/OSHA permit for shoring?
A Cal/OSHA permit is required to erect scaffolding, vertical shoring or falsework intended to be more than 36 feet high when completed, under Title 8 Section 341. Shoring below that height still needs a signed shoring layout kept on the job site.
When can temporary shores be removed?
Under Title 8 Section 1717, forms and shores (other than those for slabs on grade and slip forms) cannot come out until the employer determines the concrete has gained enough strength to support its own weight and any loads placed on it. Follow the engineer’s removal and reshoring sequence.
What types of temporary shoring are used in buildings?
Common types are vertical post shores and shoring towers under slabs and beams, raker shores that brace walls from the side, needle beams that carry a wall through an opening, and flying or dead shores that hold up a wall while a lower section is replaced.